File #: 16-5031   
Type: Consent Item Status: Agenda Ready
In control: Board of Commissioners
On agenda: 7/10/2023 Final action:
Title: Approval of Construction Contract GMP #4 with Construction Manager at Risk for the Public Health Center Project
Attachments: 1. PHC GMP-4 Item Summary.pdf, 2. GMP-4 Contract Cost Summary.pdf, 3. Project Summary Schedule - All GMPs.pdf, 4. GMP-4 Minority Participation Summary.pdf, 5. GMP-4 Bldg Concrete Bid Tab.pdf, 6. GMP-4 Bldg Elevators Bid Tab.pdf, 7. GMP-4 Bldg Gnrl Trades Bid Tab.pdf, 8. GMP-4 Bldg Roof Bid Tab.pdf, 9. GMP-4 Bldg Spray Fireproof Bid Tab.pdf, 10. GMP-4 Bldg Structural Stl Bid Tab.pdf, 11. GMP-4 Bldg Waterproof Bid Tab.pdf, 12. GMP-4 Masonry Bid Tab.pdf, 13. GMP-4 Ext Curtain Wall & Mtl Panels Bid Tab.pdf, 14. Total Project Cost Summary.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Approval of Construction Contract GMP #4 with Construction Manager at Risk for the Public Health Center Project

Recommended Action

That the Board of Commissioners:

 

1.                     Appropriates $67 million in Limited Obligation Bonds in the County Buildings Element of the County Capital Improvements Fund, and

 

2.                     Approves Guaranteed Maximum Price (GMP) #4 Contract in the amount of  $15,760,486 with the previously selected Construction Manager at Risk, Skanska USA Building, Inc. of Durham, NC for the new Public Health Center project at the Swinburne Campus in Raleigh, NC, and

 

3.                     Authorizes the County Manager to execute this construction contract with Skanska USA Building, Inc.; said contract documents to be reviewed and approved by the County Attorney.