Title
Wake County Public School System CIP 2013 Reallocations and Appropriations (Second Reading)
Recommended Action
That the Board of Commissioners approve the Board of Education’s request to reallocate and appropriate funds in CIP 2013.
1. Reallocate a total of $1,118,388 in CIP 2013, including $918,388 of contingency funds for construction at Lincoln Heights Elementary and $200,000 in startup design funds to account for scope and schedule changes at Vandora Springs Elementary
2. Appropriate a total of $47,448,387 in CIP 2013 for construction and public infrastructure at Bryan Road and Lincoln Heights Elementary schools, startup design at Vandora Springs Elementary, and design at Rolesville Elementary